A £1.75 million finish and exit facility on a stalled seven-unit scheme near Taunton, Somerset, arranged at 60% LTGDV over a 14-month term when the incumbent development facility expired with the scheme 80% built. The new facility repaid the original lender in full, funded the remaining works and carried the units through to sale. This is what actually happens when a development facility runs out of term before the scheme runs out of work.
| Location | Village on the edge of Taunton, Somerset |
| Loan amount | £1,750,000 finish and exit facility |
| Gearing | 60% LTGDV |
| GDV | £2,900,000 |
| Term | 14 months |
| Product | Finish and exit development finance, certified drawdowns on remaining works |
| Exit | Open-market sale of the seven units under agreed release pricing |
The situation
The clients were a two-partner development team building seven houses in a village on the edge of Taunton, their fourth scheme together. The original 18-month development facility had been running to plan until the main contractor went into administration at month eleven with the scheme roughly two thirds built, and the four months it took to novate the subcontracts, re-tender the remaining packages and get a replacement contractor mobilised ate the rest of the term.
By the time the facility expired the scheme was 80% built. Roofs on across all seven units, first fix complete on five, kitchens, second fix and externals still to come. The incumbent lender had granted one three-month extension with a fee and a stepped-up rate, and made it clear in writing that a second extension was not coming. The scheme needed roughly four more months of work and then a sales period, and the money to pay for it was about to be called in.
Every year we see at least one scheme in exactly this position, and it is almost never the developer's competence that put it there. Contractors fail. Programmes slip. The facility term was set eighteen months earlier against a programme that no longer exists, and the lender's patience runs out on a date that has nothing to do with where the scheme actually is.
Why the incumbent could not simply extend
People assume the incumbent lender is the natural home for more time, and sometimes they are, but a development lender at the end of its appetite is pricing its own exposure rather than your scheme. The extension already granted carried a fee and a rate step-up, a second one would have carried more of both, and expired facilities drift toward default pricing, which is where the real damage happens. The incumbent had also stopped releasing drawdowns at expiry, so the remaining works were being cashflowed out of the partners' own pockets.
The high street was never in the conversation. Part-built schemes frighten most lenders. A clearing bank cannot price a site with scaffolding on it, and even many specialist development lenders prefer to start schemes rather than rescue them, because the cost to complete someone else's build carries unknowns their credit process does not like. The lenders who write finish and exit facilities do this deliberately, and they underwrite the two things that matter: the true cost to complete, and the realism of the sales values.
My advice to any developer watching their term run down is to start the refinance conversation at least three months before expiry, not when the extension letter arrives, because a finish and exit facility takes five to seven weeks to complete and every week of overlap with an expired facility is charged at the incumbent's worst pricing.
The structure
The facility completed at £1.75 million against a GDV of £2.9 million, 60% LTGDV. Around £1.36 million redeemed the incumbent facility in full, roughly £270,000 funded the remaining works drawn against certificates, and the balance covered rolled interest and fees so the partners carried no monthly outgoing through the works and the sales period. Pricing on finish and exit money sits closer to bridging than to senior development finance, and this facility priced just under 1% per month with an arrangement fee in the standard 1% to 2% range.
The lender's QS reviewed the cost to complete before credit approval, and this is the part developers underestimate. What we have seen across the stalled schemes we have refinanced is that the developer's own cost-to-complete figure is always light, because it never carries enough contingency for opening up another contractor's work, so the QS built a contingency on top of the £270,000 and the facility was sized to carry it. Better to have the headroom and not draw it.
The 14-month term was structured as four months of works plus a ten-month sales runway across seven units. Release pricing was agreed on day one, with each sale clearing slightly more than that unit's share of the debt, so the balance falls ahead of pro rata as the scheme sells through.
How it completed
The partners came to us two weeks before the extended expiry date, which was later than ideal and cost them a period of default-rate interest with the incumbent. First call to credit-approved terms took eight working days. The valuation ran as a dual assessment, current value as standing plus GDV on completion, and the QS report on the cost to complete ran concurrently over the following fortnight. Legals took three weeks, with the incumbent's redemption statement and the replacement contractor's collateral warranties the only points of friction. Completion came just under six weeks from first call.
The incumbent was repaid in full. The replacement contractor remobilised within a week of completion, drawdowns on the remaining works ran fortnightly against certificates, and practical completion landed three weeks inside the four-month works window. The first two units went under offer while the show home was still being carpeted, which tells you what we already knew about family-house demand on the edge of Taunton.
The outcome
The £1.75 million finish and exit facility repaid the incumbent lender in full, ended the default-rate bleed, funded the remaining four months of works with a proper QS-checked contingency, and gave the scheme a ten-month sales runway at 60% LTGDV. Practical completion came three weeks early, the first sales completed inside five months, and the partners kept the margin they had spent three years building instead of handing it to an expired facility.
Frequently asked questions
What is finish and exit development finance?
Finish and exit finance refinances a part-built development, repaying the incumbent development lender, funding the remaining works and carrying the completed units through the sales period. It suits schemes where the original facility has expired or the relationship with the incumbent has broken down, and it is underwritten on the cost to complete and the sales values rather than the full ground-up development risk.
Can you refinance a part-built development?
Yes, though the lender pool is smaller than for ground-up schemes. Specialist lenders will refinance schemes that are substantially built, typically past wind and watertight, where the remaining works are clearly costed and the sales evidence supports the GDV. The further built the scheme, the better the terms, because the residual construction risk shrinks with every certified package.
What happens when a development facility expires before the scheme is finished?
The lender can charge extension fees and step the rate up, move the facility toward default pricing, stop releasing drawdowns, and in the worst case appoint receivers. Most lenders prefer a clean refinance to enforcement, but the pricing while you arrange one is punishing, which is why the refinance should start months before expiry rather than after it.
How do lenders value a part-built scheme?
Usually as a dual assessment: the current value of the site as it stands, and the gross development value on completion, alongside an independent QS review of the cost to complete. Lenders add contingency to the developer's own cost-to-complete figure, because opening up another contractor's work reliably surfaces items the original programme never priced.
How quickly can finish and exit finance complete?
Five to seven weeks from first enquiry is realistic where the developer has the build information, sales evidence and redemption figures ready. This facility completed in just under six weeks. The pace is set less by the lender and more by how quickly the QS can verify the remaining works and how cooperative the incumbent is on redemption.
Rates and terms quoted are indicative and subject to change. Actual terms depend on individual circumstances, the scheme, security and lender appetite at the time of application. Your property may be repossessed if you do not keep up repayments on a mortgage or any other debt secured on it.
We arrange finish and exit facilities on stalled and part-built schemes across the UK, from £250,000 to £250 million plus, structured around the cost to complete and the sales period rather than the original programme.
Call 03300 100315